Barrington Elementary School (renovation plus addition)

Design Elements

  • Increase of 25,000 square feet, bringing the total square footage for the building to 110,000 square feet
  • Renovated kitchen/cafeteria common area
  • 36 classrooms in six learning “neighborhoods”
  • New centralized media center
  • New outdoor learning space and playground

Please note that all design plans are subject to minor adjustments. 

Tentative Construction Timeline

As of the fall of 2018, construction for Barrington Elementary School is expected to follow this tentative timeline. The timeline may be revised during the final stage of the design process and/or during the construction process based on any potential delays that arise. 
 
Late spring/early summer 2019
Work will begin on the Barrington site. 

March 2020
Barrington will be prepped for the arrival of modular classrooms for use during the 2020-2021 school year.

Fall 2021
The renovated Barrington elementary school will open to students.