Tremont Elementary School

Tremont Elementary School (renovation and addition)

Design Elements

  • New addition of 7,000 square feet, bringing the total square footage for the building to 86,000 square feet
  • Renovation of the original two-story classroom building
  • Five new kindergarten rooms; 30 total classrooms in six learning “neighborhoods”
  • New centralized media center
  • New outdoor learning space

Please note that the final designs are subject to minor adjustments. 

Tentative Construction Timeline

As of January 2019, construction at Tremont Elementary School is expected to follow this tentative timeline. The timeline may be revised during the construction documents phase and/or during the construction process based on any potential delays that arise. 
 
March 2019
Tremont will be prepped for the arrival of modular classrooms for use during the 2019-2020 school year.

Late Spring/Early Summer 2019
Work will begin on the Tremont site.
May 19, 2019: Groundbreaking ceremonies for Barrington, Greensview, Tremont and Wickliffe elementary schools.

Fall 2020
The renovated Tremont elementary school will open to students.